If you have searched for the stages of house construction in Australia, you have likely found diagrams, checklists and vague reassurance. What those guides rarely explain is that each stage becomes a contract term with money attached. Your payment schedule is the main lever you hold over a build, and it is worth reading as an asset rather than paperwork.
This guide is for homeowners signing a major domestic building contract in Victoria, and for anyone who wants to understand what they are agreeing to before they sign. We walk through how progress payment stages are prescribed, what the fixing stage actually covers, a practical checklist for inspecting and signing off, and how to match every stage to work you can see and verify.
The rules themselves matter too. The Domestic Building Contracts Amendment Regulations 2026 have been made as statutory rule 175/2026 and commence on 31 March 2027, so they are not in force yet. You will see the $20,000 contract threshold, the shift in deposit limits, and the section 40(4) question the industry is still debating.
We hold a Domestic Builder Unlimited licence and build across Melbourne and surrounds.
Your Payment Schedule Is the Main Lever You Hold Over a Build
In Victoria, a major domestic building contract is typically paid through progress payments tied to defined stages. That makes the payment schedule the document carrying your real risk, not the headline quote. Progress payments are meant to track work actually done, so every stage should describe something you can walk onto the site and inspect with your own eyes.
Paying ahead of completed work is the most common way homeowners hand leverage back. Once a stage is paid, the only pressure left is goodwill. A schedule that names a stage without defining its scope is hard to dispute later. One tied to defined deliverables gives you something concrete to measure the claim against.
This guide is written from the perspective of Builda Group, a licensed Victorian residential builder holding a Domestic Builder Unlimited licence and working across Melbourne and surrounds. For a closer look at how claims are structured on local builds, see how payment schedules work.
How Victorian Progress Payment Stages Are Prescribed
The schedule sits inside a legal framework that is about to change.
Victoria’s prescribed progress payment stages come from the Domestic Building Contracts Regulations, so check your own schedule’s wording and percentages against the principal Regulations, not an online summary, this one included.
Most major contracts move through a recognisable sequence: base, frame, lock-up, fixing and completion, each tied to a percentage of the contract price. From 31 March 2027, a major contract to build a home using less than 30% modern methods of construction will have those stages, and the maximum percentage a builder can demand, recover or retain at each one, set by regulation, as the Department outlines.
Two groups sit outside the prescribed stages: projects of $1 million or more per dwelling, and small second dwellings currently up to 80 m². For that second category, payments must still reflect progress on site.
The first thing to question is a stage percentage that looks like it covers work not yet done. Raise it before you sign, while the schedule is still a draft rather than a paid claim. Once claims start arriving, reading a progress claim properly turns that comparison into routine.
Fixing Stage Definition: What Fixing Actually Covers in Victoria
Within that prescribed sequence, fixing is generally the internal fit-out stage, when skirting, architraves, internal doors and hardware, cornices, joinery and cabinetry, wardrobes and shelving go in once the building is closed up and weathertight.
Read the actual wording rather than trusting how any builder happens to use the term on site. Your contract wording is the reference point, and the current deposit and payment rules set out the legal framework around it. Our Melbourne build stage guide sets out where each checkpoint falls in the programme.
Fixing and fit-off are usually treated as separate stages. Taps, appliances, light fittings and switch plates are generally connected later, so a fixing claim covering work that is really fit-off means you have paid early.
Services should already be behind the plaster before fixing begins. Services are generally roughed in earlier in the build, so visible cabling or unfinished penetrations at fixing are a warning sign worth writing down.
Wet area tiling, waterproofing and cabinet installation shift between contracts. Check where your contract places them before you compare one schedule against another.
Fixing Stage Checklist: What to Inspect Before You Sign
Once fixing is complete on site, inspect before you pay.
Walk every room with the approved plans and your contract inclusions list in hand. Write defects down as you go; do not rely on raising them verbally on the day.
Use our stage-by-stage inspection checklist to record the walk-through. Check:
- skirting and architrave joints
- door clearances, swing direction and hardware operation
- cornice lines and ceiling set-out against the plan
Open and close every cabinet, drawer and wardrobe. Check alignment, gaps, benchtop joins, and confirm the specified materials and hardware were actually supplied.
In wet areas, confirm waterproofing and tiling are complete to the contract. Photograph every defect before trades move on, because paint and fit-off can hide the evidence.
Send your defect list in writing before you sign the progress claim. Ask for a date each item will be fixed. Signing off is what releases the payment, so keep the claim unsigned until the list is acknowledged and the fix dates are clear.
Matching Each Stage to Work You Can Inspect and Sign Off
Signing off should never be a formality, and that discipline applies at every stage. At base, check set-out, excavation, the slab, damp-proofing and service penetrations are complete and visible, plus any slab certification your contract requires. At frame, confirm the frame, bracing and roof structure are complete and that window and door openings match the plan. Book an independent frame inspection before walls hide the work; framed work is far easier to put right before it is covered up.
At lock-up, the roof cover, windows, external doors and cladding should be installed, so the building is genuinely secure and internal trades can work inside. Fixing should cover only the fit-out listed in your contract. Completion is where the defects list is closed out, certificates and approvals are handed over, and keys change hands. A project management guide for homeowners can help you track this sequence.
The 2026 Rules Are Made, Not Draft, and Not in Force Until 31 March 2027
That stage-by-stage discipline matters even more now, because the payment rules themselves are changing. The Domestic Building Contracts Amendment Regulations 2026 are not a draft or a proposal. They have been made as statutory rule 175/2026 and are listed on the Victorian legislation site as made, so any page still calling them draft is out of date.
The Department states they commence on 31 March 2027. No contract signed today is governed by them yet.
The notice of decision was gazetted on 26 October 2026, after consultation ran from 18 August to 16 September 2026 and drew 17 written submissions and 23 survey responses. A caretaker period from 6pm on 3 November 2026 also sits on that timeline, which matters if you are watching for further announcements.
What Changes on 31 March 2027: Thresholds, Deposits and Payments
From 31 March 2027, the major domestic building contract threshold rises from $10,000 to $20,000. Building Practitioners Board guidance that still cites $10,000 will lag until it is updated, so check the threshold that applies to your contract date.

Deposit limits will rise and vary by modern methods of construction (MMC) category. Read the figures from the authorised regulations rather than a summary. A Victorian build budget example can help you see how stage percentages affect cash flow.
The Housing Industry Association (HIA) welcomed a new site preparation stage in its consultation submission, but its inclusion is not confirmed in published final extracts. Only the authorised regulations settle whether a site preparation stage exists, so check the instrument itself before relying on it.
Exemptions remain: projects of $1 million or more per dwelling can agree their own arrangements, and small second dwellings currently up to 80 m² are exempt from prescribed stages. For those second dwellings, payments must still reflect progress, not a calendar.
The Section 40 Question: Why the Industry Wants Agreed Schedules Kept
Exemptions aside, the 2026 Regulations sharpen a deeper structural debate. The Housing Industry Association’s central objection is the removal of the ability for clients and builders to agree their own stages and schedules. It argues this makes the regime overly prescriptive and built for an older cost structure. The HIA also states its members deliver over 80% of Australia’s new housing supply each year; treat that as an industry-body claim, not an independently verified figure. Check the section 40 wording in the authorised regulations, and confirm the section 40(3) and 40(4) provisions in the instruments themselves before quoting any summary of them as fact.
For a homeowner, the practical question is where negotiation sits. A builder and client who can agree a schedule can align payments to a specific site sequence. A fully prescribed schedule takes that option away. Some stakeholder requests were deferred to the sunsetting regulation review in 2027/28, so further movement after commencement is possible. If you are planning new home developments in Melbourne, ask where that discretion sits before signing.
What to Do Now, Whether You Sign Before or After Commencement
The transition question and the section 40 debate land you in the same place: paperwork. Here is what to do with it.
Read your payment schedule stage by stage against the work each stage claims to cover, before you sign. Where a stage is named but its scope is never defined, ask for that scope in writing. Fixing is the obvious example: get the contract to state how cabinetry, tiling and fit-off are split, so a later claim cannot be redefined on you.
Then ask your builder, in writing, how the 31 March 2027 commencement applies to a contract signed before that date. The published material does not settle transition arrangements. Do not assume any; get an answer you can file.
If assessing framed work or fit-out is outside your experience, book an independent inspection at frame and at fixing. Those are the two points where errors are still cheap to correct.
Finally, keep every progress claim, inspection note, photograph and defect list in one file. A stage dispute turns on what you can show was outstanding when you paid.
The Stage Schedule Is Where You Win or Lose Leverage
Filing those records only pays off if the schedule itself was built to be checked, and a schedule built to be checked makes every claim map to work you can inspect, photograph and list before you pay. Before you sign, line the prescribed stages up against your contract and confirm how the 31 March 2027 commencement affects your start date. Ask, plainly, where the fixing stage begins and ends. If the answer drifts into generalities, request it in writing with the scope named. A defined stage is the one piece of paperwork that keeps a build moving on your terms, not the builder’s.
Conclusion
The lesson is straightforward: your payment schedule is your main lever, and that leverage disappears when a stage pays on a date or bare percentage. Make every claim map to work you can inspect, photograph and list before you pay. Know the prescribed Victorian stages, define the fixing stage in writing, and keep one file of claims, notes, photos and defects. The 2026 rule changes are not in force until 31 March 2027, and the published material does not settle how they apply to contracts signed earlier. Your next step is to ask your builder, in writing, how commencement applies to your contract and where fixing starts and ends. Our Domestic Builder Unlimited licence supports the work we do across Melbourne and surrounds; use it to insist on defined, inspectable stages.